PRJ-2026-036On track9HandoverConstruction

Rainwater Harvesting & Small Dams

Add to watchlist

Nine small dams and recharge channels to harvest rainwater in the highlands.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩

Planned ⁦99%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure31 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate19 April 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate13 November 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate5 December 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 February 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate17 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate1 September 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate31 October 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-10-31⁩
    Budget
    SAR 67M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-10-06⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-12-08⁩
    ⁦+38⁩ days
    Budget
    SAR 67M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Waleed O. Al-Juhani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-10-31⁩⁦2026-12-08⁩

⁦+38⁩ days

Budget

SAR 67MSAR 67M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-07
  • Project plan approved⁦+13⁩
  • Designs approved⁦+22⁩
  • Build complete⁦+38⁩
  • Testing & acceptance complete⁦+52⁩
  • Final handover⁦+38⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.08⁩
  • 2Design & permits⁦+0.16⁩
  • 3Civil works⁦+1.85⁩
  • 4MEP works⁦+0.41⁩
  • 5Handover⁦−0.82⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Waleed O. Al-Juhani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-10-06⁩by Eng. Turki A. Al-Anazi