Preliminary handover certificate — Abha administrative court

InternalPendingV1

Preliminary handover certificate for the Abha administrative court rehabilitation, awaiting the handover committee’s signature.

More

Internal

Kingdom of Saudi Arabia

Board of Grievances

Projects Follow-up Office (EPMO)

Code
DOC-0220
Version
V1
Date
2026-10-26

Preliminary handover certificate — Abha administrative court

Abha Administrative Court Rehabilitation

Preliminary handover certificate — Abha administrative court

Project
Abha Administrative Court Rehabilitation (⁦PRJ-2026-036⁩)
Project manager
Eng. Waleed O. Al-Juhani
Budget
SAR ⁦67.0M⁩
Progress
⁦97%⁩ actual against ⁦99%⁩ planned
Forecast finish
⁦2026-11-12⁩

The handover committee certifies that the works listed were carried out to the contract and specification, with the attached snag list to be closed during the defects period.

Prepared by

Eng. Waleed O. Al-Juhani
Issued from Munjaz — valid only once approved electronically1 / 1