PRJ-2026-010On track7ExecutionConstruction

Solar Power for Government Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 government buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+5

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦58%⁩ done against ⁦57%⁩ planned.

SPI ⁦1.02⁩, CPI ⁦1.01⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦90%⁩ of budget

55.1M/ 96M950Kprojected saving(⁦1.0%⁩)
Actual spend
55.1M
Committed
86.5M
Approved budget
96M
Estimate at completion
95.1M

Next milestones

  • Provisional acceptance⁦2027-02-20⁩was ⁦2027-02-26⁩On track
  • Closure⁦2027-04-22⁩was ⁦2027-04-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 5.2M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦1⁩ of ⁦4⁩ approved

  • Project management planDLV-010-1 · V1Eng. Mishari K. Al-Otaibi574 days overdue2025-04-024 Shawwal 1446 AHIn review
  • Main deliverable — stage 1DLV-010-2 · V1Eng. Bandar M. Al-Shammari⁦2026-04-09⁩2026-04-0921 Shawwal 1447 AHApproved
  • Main deliverable — final stageDLV-010-3 · V1Eng. Bandar M. Al-ShammariIn 74 days2027-01-102 Shaʻban 1448 AHIn progress
  • Final reportDLV-010-4 · V0Eng. Bandar M. Al-ShammariIn 184 days2027-04-3023 Dhuʻl-Qiʻdah 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Mishari K. Al-Otaibi · Director, Sustainability & EnvironmentEng. Bandar M. Al-Shammari · Deputy, Infrastructure
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentProject managerP-028m.alotaibi@alwaha.gov.sa⁦45%⁩
  • Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDeputy, InfrastructureProject sponsorP-013b.alshammari@alwaha.gov.sa⁦15%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close