Board of GrievancesMunjaz10My actionsNotifications

Electricity bill savings

On track

Cost saving · Solar Power for Court Buildings

Baseline

0 SAR M

At go-live, ⁦2026-04-26⁩

Latest reading

2.60 SAR M

6 mo reading

Target after 24 months

9.30 SAR M

On ⁦2028-04-26⁩

Target trajectory vs realised

Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.

Target trajectory vs realised
  • Realised
  • Target trajectory
  • Forecast
Target trajectory vs realised
PeriodRealisedTarget trajectory
2026-040 SAR M0 SAR M
2026-050.24 SAR M0.37 SAR M
2026-060.78 SAR M0.73 SAR M
2026-071.20 SAR M1.10 SAR M
2026-081.55 SAR M1.57 SAR M
2026-092.15 SAR M2.03 SAR M
2026-102.60 SAR M2.50 SAR M
2026-11 (Forecast)3.10 SAR M2.98 SAR M
2026-12 (Forecast)3.61 SAR M3.47 SAR M
2027-01 (Forecast)4.11 SAR M3.95 SAR M
2027-02 (Forecast)4.61 SAR M4.43 SAR M
2027-03 (Forecast)5.11 SAR M4.92 SAR M
2027-04 (Forecast)5.62 SAR M5.40 SAR M
2027-05 (Forecast)5.95 SAR M5.73 SAR M
2027-06 (Forecast)6.29 SAR M6.05 SAR M
2027-07 (Forecast)6.63 SAR M6.38 SAR M
2027-08 (Forecast)6.97 SAR M6.70 SAR M
2027-09 (Forecast)7.31 SAR M7.03 SAR M
2027-10 (Forecast)7.64 SAR M7.35 SAR M
2027-11 (Forecast)7.98 SAR M7.68 SAR M
2027-12 (Forecast)8.32 SAR M8 SAR M
2028-01 (Forecast)8.66 SAR M8.33 SAR M
2028-02 (Forecast)9 SAR M8.65 SAR M
2028-03 (Forecast)9.33 SAR M8.98 SAR M
2028-04 (Forecast)9.67 SAR M9.30 SAR M

Measurement schedule

Counted from go-live on ⁦2026-04-26⁩ · data read Monthly

  1. 3

    After 3 months

    2026-07-2612 Safar 1448 AH·Expected 1.10 SAR M·Actual 1.20 SAR M

    to plan⁦109%⁩
  2. 6

    After 6 months

    2026-10-2615 Jumada I 1448 AH·Expected 2.50 SAR M·Actual 2.60 SAR M

    to plan⁦104%⁩
  3. 12

    After 12 months

    2027-04-2619 Dhuʻl-Qiʻdah 1448 AH·Expected 5.40 SAR M

    In 180 days2027-04-2619 Dhuʻl-Qiʻdah 1448 AH
  4. 24

    After 24 months

    2028-04-261 Dhuʻl-Hijjah 1449 AH·Expected 9.30 SAR M

    In 546 days2028-04-261 Dhuʻl-Hijjah 1449 AH

Evidence

5 files backing the readings

  • Measurement data extract — 6 mo

    2026-10-26 · Haifa S. Al-Ruwaili · ⁦138⁩ KB

  • Benefit measurement report — 6 mo

    2026-10-26 · Haifa S. Al-Ruwaili · ⁦986⁩ KB

  • Measurement data extract — 3 mo

    2026-07-26 · Haifa S. Al-Ruwaili · ⁦117⁩ KB

  • Benefit measurement report — 3 mo

    2026-07-26 · Haifa S. Al-Ruwaili · ⁦923⁩ KB

  • Approved benefit profile — BEN-013

    2026-02-26 · Eng. Mishari K. Al-Otaibi · ⁦412⁩ KB

Corrective actions

What is being done to bring the benefit back to plan

The benefit is on plan and needs no actions.

Activity

26 October 2026

  1. Milestone: Haifa S. Al-Ruwaili recorded the ⁦6⁩ mo reading: ⁦2.60⁩ SAR M

    2026-10-26 10:30

26 July 2026

  1. Milestone: Haifa S. Al-Ruwaili recorded the ⁦3⁩ mo reading: ⁦1.20⁩ SAR M

    2026-07-26 10:30

26 February 2026

  1. Approval: Eng. Mishari K. Al-Otaibi approved the benefit profile and its baseline

    2026-02-26 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close