PRJ-2026-010On track7ExecutionConstruction

Solar Power for Court Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 court and Board buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-04-30⁩
    Budget
    SAR 96M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-03-02⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-04-30⁩
    Budget
    SAR 96M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Mishari K. Al-Otaibi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-04-30⁩⁦2027-04-30⁩

⁦0⁩ days

Budget

SAR 96MSAR 96M

⁦0.00⁩ SAR M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+44⁩
  • Designs approved⁦+78⁩
  • Build complete⁦+127⁩
  • Testing & acceptance complete⁦+69⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.12⁩
  • 2Design & permits⁦+0.23⁩
  • 3Civil works⁦+2.65⁩
  • 4MEP works⁦−0.39⁩
  • 5Handover⁦−0.20⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Mishari K. Al-Otaibi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-03-02⁩by Eng. Turki A. Al-Anazi