PRJ-2026-010On track7ExecutionConstruction
Solar Power for Court Buildings
Add to watchlist18 MW of rooftop and carport solar across 64 court and Board buildings.
Project managerEng. Mishari K. Al-OtaibiSponsorEng. Turki A. Al-AnaziProgrammeFacilities Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 96M
Actual cost
SAR 55.1M
57% of budget
Progress
58%
Planned 57%
Estimate at completion
SAR 95.1M
SPI · CPI
1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Forecast finish
2027-04-22
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control10 January 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started