PRJ-2026-010On track7ExecutionConstruction

Solar Power for Court Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 court and Board buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

2 members, about ⁦0.6⁩ full-time equivalents

Leadership

2 members

  • Eng. Mishari K. Al-OtaibiProject manager⁦45%⁩Allocated ⁦105%⁩ across all projectsA
  • Eng. Bandar M. Al-ShammariProject sponsor⁦15%⁩Allocated ⁦105%⁩ across all projectsR

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Turki A. Al-AnaziManage closelyEng. Bandar M. Al-ShammariManage closelyProjects Follow-up Office (EPMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedSustainable Energy Contracting Est.Manage closely

Interest

Project sponsor

Eng. Turki A. Al-Anazi

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-20⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Turki A. Al-AnaziProject sponsorDecisions and fundingSupportiveLeadingEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa⁦2026-10-20⁩
Eng. Bandar M. Al-ShammariBusiness ownerAccepts deliverables, owns benefitsNeutralLeadingEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa⁦2026-10-23⁩
Projects Follow-up Office (EPMO)GovernanceCompliance and data qualitySupportiveEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa⁦2026-10-17⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@bog.gov.sa⁦2026-10-14⁩
Sustainable Energy Contracting Est.Main vendorDelivers the contracted workSupportiveEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa⁦2026-10-24⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa⁦2026-09-26⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Mishari K. Al-Otaibi⁦2026-11-15⁩
  • Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Mishari K. Al-Otaibi⁦2026-11-03⁩
  • EPMOData and indicator updatesWeeklyDashboardEng. Mishari K. Al-Otaibi⁦2026-10-31⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Mishari K. Al-OtaibiAt launch

Coming up

By date

  1. 312026-10EPMODashboard · Weekly
  2. 032026-11Business ownerEmail · Fortnightly
  3. 152026-11Project sponsorMeeting · Monthly