PRJ-2026-010On track7ExecutionConstruction

Solar Power for Court Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 court and Board buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
1On track
1At risk
0Late
Average delay64 days
Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2026-06-21⁩Forecast / actual: ⁦2026-10-26⁩Delay: 127 daysG3 +127
Executive
Project plan approvedPlanned: ⁦2025-08-12⁩Forecast / actual: ⁦2025-09-25⁩Delay: 44 daysG1 +44
Payment
Final handoverPlanned: ⁦2027-04-30⁩Forecast / actual: ⁦2027-04-30⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-12-26⁩Forecast / actual: ⁦2027-03-05⁩Delay: 69 daysG4 +69
Project
Designs approvedPlanned: ⁦2025-12-15⁩Forecast / actual: ⁦2026-03-03⁩Delay: 78 daysG2 +78

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-08-12⁩⁦2025-09-25⁩⁦+44⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-15⁩⁦2026-03-03⁩⁦+78⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-06-21⁩⁦2026-10-26⁩⁦+127⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-12-26⁩⁦2027-03-05⁩⁦+69⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-04-30⁩⁦2027-04-30⁩On timeEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline010-D1ApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-06-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting010-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-08-12⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design010-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-10-13⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals010-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-12-15⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation010-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-02-16⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure010-D6ApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-04-19⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩