Solar Power for Court Buildings
Add to watchlist18 MW of rooftop and carport solar across 64 court and Board buildings.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 57%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control10 January 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
18 MW of rooftop and carport solar across 64 court and Board buildings.
In scope
- 18 MW of rooftop and carport solar across 64 court and Board buildings.
- Saudi Building Code compliance
- An approved plan to keep the courts sitting during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2025-04-06
Baseline approved at the planning gate
Budget96MFinish2027-04-30
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-010-01 | Reach the target number of courtrooms | Business | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-010-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | SB-1 | |
| REQ-010-03 | Courts keep sitting during the works | Functional | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-010-04 | Saudi Building Code | Regulatory | Should | In progress | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | SB-1 | |
| REQ-010-05 | Civil-defence requirements | Regulatory | Should | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-010-06 | Site and systems security | Security | Could | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. No requirement has a gap.