RSK-0041Solar Power for Court Buildings
Falling global panel prices allow more capacity within budget
A risk's detail, response, contingency and residual risk.
Risk statement
From enabler to opportunity to benefit — with the actions that seize it and the fallback
Enabler
Global solar panel prices down 18% this year
Actions to seize it
- Renegotiate the second panel batch
- Add three administrative courts to the installation scope
2 / 2
Opportunity
More installed capacity on court buildings within the same budget
A quote under SAR 2.1 per watt
Fallback
If prices rise again, keep to the original scope
Benefit
2.4 MW more and about SAR 5.2M a year more in power savings
Assessment
The level before and after the response
Inherent
Residual
Potential value
SAR 5.2M
Residual
No reduction expected — the response is to accept
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director
Last reviewed 3 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Mishari K. Al-Otaibi
Currently followed up here- 2
Programme manager
Eng. Mishari K. Al-Otaibi
- 3
EPMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the EPMO director’s decision
Mitigation plan
Actions to seize the opportunity, with owners and dates
Renegotiate the second panel batch
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saIn progressIn 33 days2026-11-3020 Jumada II 1448 AHAdd three administrative courts to the installation scope
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saNot startedIn 53 days2026-12-2011 Rajab 1448 AH
Trigger
A quote under SAR 2.1 per watt
Fallback
If prices rise again, keep to the original scope
Opportunity strategy
§26 — choose how you will seize it