Energy Retrofit of Existing Court Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Planned 9%
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
ProcurementPhase 6 of 11
Next gate:Execution24 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-05-18 | 2026-10-26 | +161 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-08-08 | 2027-01-16 | +161 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Late | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2026-12-08 | 2027-05-04 | +147 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-09 | 2027-08-20 | +133 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-06-30 | 2027-10-31 | +123 days | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline026-D1 | Approved | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-04-07 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting026-D2 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-05-18 | V1 | 2 of 2 |
| Deliverable: Detailed design026-D3 | Submitted | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-06-28 | V1 | 1 of 2 |
| Deliverable: Permits & approvals026-D4 | Draft | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-08-08 | V0 | 0 of 2 |
| Deliverable: Site works & excavation026-D5 | Draft | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-09-17 | V0 | 0 of 2 |
| Deliverable: Structure026-D6 | Draft | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-10-28 | V0 | 0 of 2 |