PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

1Achieved
0On track
3At risk
1Late
Average delay145 days
Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-12-08⁩Forecast / actual: ⁦2027-05-04⁩Delay: 147 daysG3 +147
Executive
Project plan approvedPlanned: ⁦2026-05-18⁩Forecast / actual: ⁦2026-10-26⁩Delay: 161 daysG1 +161
Payment
Final handoverPlanned: ⁦2027-06-30⁩Forecast / actual: ⁦2027-10-31⁩Delay: 123 daysG5 +123
Regulatory
Testing & acceptance completePlanned: ⁦2027-04-09⁩Forecast / actual: ⁦2027-08-20⁩Delay: 133 daysG4 +133
Project
Designs approvedPlanned: ⁦2026-08-08⁩Forecast / actual: ⁦2027-01-16⁩Delay: 161 daysG2 +161

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-05-18⁩⁦2026-10-26⁩⁦+161⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-08-08⁩⁦2027-01-16⁩⁦+161⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saLate0Not requested
Build completeMS-G3Contractual⁦2026-12-08⁩⁦2027-05-04⁩⁦+147⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-04-09⁩⁦2027-08-20⁩⁦+133⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-06-30⁩⁦2027-10-31⁩⁦+123⁩ daysEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline026-D1ApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-04-07⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting026-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-05-18⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design026-D3SubmittedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-06-28⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Permits & approvals026-D4DraftSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-08-08⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Site works & excavation026-D5DraftSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-09-17⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Structure026-D6DraftEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saEng. Bandar M. Al-Shammari⁦2026-10-28⁩V0⁦0⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩