PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project lifecycle and its gates

Current phase: Procurement. Pick a gate on the track to review it.

  1. Gate into «Feasibility»DecisionConditional goDate15 August 2025Mandatory criteria met, with points to close during the next phase.IdeaComplete
  2. Gate into «Initiation»DecisionGoDate3 December 2025All criteria and required documents met.FeasibilityComplete
  3. Gate into «Planning»DecisionGoDate1 February 2026All criteria and required documents met.InitiationComplete
  4. Gate into «Approval»DecisionGoDate27 February 2026All criteria and required documents met.PlanningComplete
  5. Gate into «Procurement»DecisionGoDate14 March 2026All criteria and required documents met.ApprovalComplete
  6. Gate into «Execution»DecisionNot held yetDate24 April 2026ProcurementCurrent phaseCurrent phase
  7. Gate into «Monitoring & Control»DecisionNot held yet7ExecutionNot started
  8. Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
  9. Gate into «Closure»DecisionNot held yet9HandoverNot started
  10. Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
  11. 11Benefits RealizationNot started
G5Next gateBid Evaluation & Award Committee

Award gate — into execution

6Procurement7ExecutionPlanned for ⁦2026-04-24⁩187 days overdue2026-04-247 Dhuʻl-Qiʻdah 1447 AH
62/100

Gate readiness

Enough for a conditional go only

Automated control: no move until the criteria are met

  • ⁦2⁩ mandatory checklist items open
  • ⁦2⁩ required documents not approved
  • ⁦2⁩ mandatory criteria under ⁦70⁩ points
  • Weighted score ⁦62⁩ under the pass mark ⁦75⁩

Checklist

⁦2⁩ of ⁦4⁩ done

  • Contract signed, guarantees lodgedMandatory
  • Vendor detailed planMandatory
  • Execution kick-off heldMandatory
  • Post-award baseline approvedMandatory

Required documents

⁦1⁩ of ⁦3⁩ approved

  • Signed contractNot submitted
  • Vendor planApproved · V1
  • Kick-off minutesNot submitted

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Vendor and named-team readinessweight ⁦35⁩%Not met

    Awaiting evidence from the project team.

  • Post-award baseline approvedweight ⁦35⁩%Not met

    Awaiting evidence from the project team.

  • Test and quality planweight ⁦30⁩%

    Awaiting evidence from the project team.

Approvers

Bid Evaluation & Award Committee

  • Munirah A. Al-KhalidiAward committee chairVote pending
  • Sarah A. Al-QarniProject sponsorVote pending
  • Dr. Noura M. Al-OtaibiEPMO directorVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.