PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Scope statement

What the project delivers, what it does not, and when a deliverable counts as accepted.

HVAC and lighting retrofits in ⁦34⁩ court buildings through ESCOs on performance contracts.

In scope

  • HVAC and lighting retrofits in ⁦34⁩ court buildings through ESCOs on performance contracts.
  • Saudi Building Code compliance
  • An approved plan to keep the courts sitting during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the business owner
  • Main deliverable — final stageMeets the approved specification, signed off by the business owner

Scope baseline

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2026-02-24⁩

    Baseline approved at the planning gate

    Budget33MFinish⁦2027-06-30⁩

Requirements register

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦0%⁩

0/6 · linked to a deliverable, task and test

Test passed

⁦0%⁩

0/6 · test result is a pass

Accepted

⁦0%⁩

0/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-026-01Reach the target number of courtroomsBusinessMustApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saSB-1
REQ-026-02Meet the approved technical specsTechnicalMustApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saSB-1
REQ-026-03Courts keep sitting during the worksFunctionalMustApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saSB-1
REQ-026-04Saudi Building CodeRegulatoryShouldApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saSB-1
REQ-026-05Civil-defence requirementsRegulatoryCouldApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saSB-1
REQ-026-06Site and systems securitySecurityCouldApprovedEng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrix

Requirement → deliverable → task → test → acceptance. ⁦6⁩ requirements have a gap.