Energy Retrofit of Existing Court Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Planned 9%
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
ProcurementPhase 6 of 11
Next gate:Execution24 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started