PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Energy Retrofit of Existing Court Buildings (ESCO)

APPROVEDV2Approved ⁦2026-01-30⁩

1Project identity

Project name
Energy Retrofit of Existing Court Buildings (ESCO)
Project code
PRJ-2026-026
Sponsor
Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa
Project manager
Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyP-028m.alotaibi@bog.gov.sa
Business owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa
Portfolio & programme
Facilities Rehabilitation & Sustainability PortfolioFacilities Rehabilitation & Efficiency Programme
Type & methodology
Infrastructure · Waterfall
Current phase
6Procurement

2Background & rationale

HVAC and lighting retrofits in ⁦34⁩ court buildings through ESCOs on performance contracts.

3Objectives

  1. 1Make judicial facilities efficient and sustainable
  2. 2Improve financial planning and diversify revenue

4Scope

In scope

  • HVAC and lighting retrofits in ⁦34⁩ court buildings through ESCOs on performance contracts.
  • Saudi Building Code compliance
  • An approved plan to keep the courts sitting during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep the courts sitting during the works
  3. 3Civil-defence requirements

6Deliverables

1Project management plan⁦2026-02-22⁩
2Main deliverable — stage 1⁦2026-10-21⁩
3Main deliverable — final stage⁦2027-04-19⁩
4Final report⁦2027-06-30⁩

7Key milestones

  1. Charter approved⁦2026-01-30⁩
  2. Contract signed⁦2026-04-24⁩
  3. 50% of works complete⁦2026-10-21⁩
  4. Provisional acceptance⁦2027-05-20⁩
  5. Closure⁦2027-06-30⁩

8Budget

  • Main contract⁦72.1%⁩23.8M
  • Supervision & consulting⁦13.6%⁩4.5M
  • Internal team⁦9.1%⁩3M
  • Contingency reserve (⁦5%⁩)⁦5.2%⁩1.7M
The owning sector’s approved budgetTotal33M

9Timeline

Start
2026-02-0113 Shaʻban 1447 AH
Baseline finish
2027-06-3025 Muharram 1449 AH
Duration
⁦17⁩ months

10Key risks

  • HighFunding left out of the ⁦2027⁩ budget, keeping the tender suspended

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board