Original
Original baseline
- Finish
- 2026-11-30
- Budget
- SAR 144.9M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Majed S. Al-Rasheed
A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Planned 80%
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control7 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-04-06 · by Eng. Majed S. Al-Rasheed
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Omar H. Bawazir
What changed from version A to version B
Finish
2026-11-302027-01-09
+40 days
Budget
SAR 144.9MSAR 148M
+3.10 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference