PRJ-2026-003At risk7ExecutionWaterfall

Board Backup Data Centre

Add to watchlist

A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩

Planned ⁦80%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control7 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 October 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate6 May 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate11 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Board Backup Data Centre

APPROVEDV2Approved ⁦2025-04-04⁩

1Project identity

Project name
Board Backup Data Centre
Project code
PRJ-2026-003
Sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa
Project manager
Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa
Business owner
Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa
Portfolio & programme
Technology & Enterprise Systems PortfolioDigital Infrastructure Programme
Type & methodology
IT · Waterfall
Current phase
7Execution

2Background & rationale

A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.

3Objectives

  1. 1Build secure, reliable, cloud-first technology

4Scope

In scope

  • A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2025-04-30⁩
2Main deliverable — stage 1⁦2026-02-08⁩
3Main deliverable — final stage⁦2026-09-07⁩
4Final report⁦2026-11-30⁩

7Key milestones

  1. Charter approved⁦2025-04-04⁩
  2. Contract signed⁦2025-07-11⁩
  3. 50% of works complete⁦2026-02-08⁩
  4. Provisional acceptance⁦2026-10-13⁩
  5. Closure⁦2026-11-30⁩

8Budget

  • Main contract⁦72.0%⁩106.6M
  • Supervision & consulting⁦14.0%⁩20.7M
  • Internal team⁦9.0%⁩13.3M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩7.4M
The owning sector’s approved budgetTotal148M

9Timeline

Start
2025-04-068 Shawwal 1446 AH
Baseline finish
2026-11-3020 Jumada II 1448 AH
Duration
⁦20⁩ months

10Key risks

  • HighExchange-rate swings on imported equipment without fixed prices
  • MediumLate delivery of cooling units and standby generators

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board