PRJ-2026-003At risk7ExecutionWaterfall

Board Backup Data Centre

Add to watchlist

A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩

Planned ⁦80%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control7 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 October 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate6 May 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate11 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project lifecycle and its gates

Current phase: Execution. Pick a gate on the track to review it.

  1. Gate into «Feasibility»DecisionConditional goDate18 October 2024Mandatory criteria met, with points to close during the next phase.IdeaComplete
  2. Gate into «Initiation»DecisionGoDate5 February 2025All criteria and required documents met.FeasibilityComplete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
  4. Gate into «Approval»DecisionConditional goDate6 May 2025Mandatory criteria met, with points to close during the next phase.PlanningComplete
  5. Gate into «Procurement»DecisionGoDate24 May 2025All criteria and required documents met.ApprovalComplete
  6. Gate into «Execution»DecisionGoDate11 July 2025All criteria and required documents met.ProcurementComplete
  7. Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026ExecutionCurrent phaseCurrent phase
  8. Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
  9. Gate into «Closure»DecisionNot held yet9HandoverNot started
  10. Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
  11. 11Benefits RealizationNot started
G6Next gateProjects Steering Committee

Operational readiness gate — into hypercare & monitoring

7Execution8Monitoring & ControlPlanned for ⁦2026-09-07⁩51 days overdue2026-09-0725 Rabiʻ I 1448 AH
77/100

Gate readiness

Meets the pass mark

Automated control: no move until the criteria are met

  • ⁦1⁩ mandatory checklist item open
  • ⁦3⁩ required documents not approved

Checklist

⁦4⁩ of ⁦7⁩ done

  • All in-scope services builtMandatory
  • User acceptance testing passedMandatory
  • Penetration test passed — no critical/high findingsMandatory
  • Data migrated and reconciledMandatory
  • Operations & support plan, SLAMandatory
  • Users trained — judges, clerks and staff
  • Launch rollback plan

Required documents

⁦1⁩ of ⁦4⁩ approved

  • UAT reportNot submitted
  • Penetration test reportApproved · V1
  • Operations & support planNot submitted
  • Data migration reconciliationSubmitted — awaiting acceptance · V1

Criteria and score

Go from ⁦75⁩, conditional from ⁦60⁩; a mandatory criterion is met from ⁦70⁩.

  • Deliverables completeweight ⁦30⁩%Met

    Awaiting evidence from the project team.

  • Quality & securityweight ⁦30⁩%Met

    Awaiting evidence from the project team.

  • Operations & support readinessweight ⁦20⁩%Met

    Awaiting evidence from the project team.

  • User & change readinessweight ⁦20⁩%

    Awaiting evidence from the project team.

Approvers

Projects Steering Committee

  • Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
  • Eng. Majed S. Al-RasheedProject sponsorVote pending
  • Dr. Noura M. Al-OtaibiEPMO directorVote pending
  • Eng. Nayef H. Al-BuqamiBusiness ownerVote pending

Gate decision

The decision and its rationale go into the gate log and to the team.

What is the decision based on? It stays in the log.0 / 600