Board Backup Data Centre
Add to watchlistA Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Planned 80%
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control7 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate18 October 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate6 May 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate24 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate11 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-19 | 2025-10-18 | +60 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-01 | 2026-03-17 | +106 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-06 | 2026-10-26 | +173 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-18 | 2026-12-08 | +112 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2027-01-09 | +40 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline003-D1 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-06-28 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting003-D2 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-08-19 | V1 | 2 of 2 |
| Deliverable: Business requirements003-D3 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-10-10 | V1 | 2 of 2 |
| Deliverable: Solution design003-D4 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-12-01 | V1 | 2 of 2 |
| Deliverable: Release 1003-D5 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-01-22 | V1 | 2 of 2 |
| Deliverable: Release 2003-D6 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-03-15 | V1 | 2 of 2 |