PRJ-2026-003At risk7ExecutionWaterfall

Board Backup Data Centre

Add to watchlist

A Tier III backup data centre that keeps Mueen and the judicial systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩

Planned ⁦80%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control7 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 October 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate6 May 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate24 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate11 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate7 September 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started