CR-2026-010Wadi Al-Rummah Bridge
Redesign the foundations of piers 12 to 16
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 8.4MCurrent budgetSAR 345M
After the changeSAR 353.4M
+2.4%
Schedule
+55 d- Baseline finish2027-05-31
- New finish2027-07-25
Risk
−12Treats the bridge’s critical risk
Benefits
0%No effect on benefits
0% of expected benefits
Reason for change
Unforeseen ground at piers 12 to 16
Business justification
The current design misses the required safety factor
PMO recommendation
ApproveThe PMO recommends urgent approval: every day of delay costs SAR 150K
Approval workflow
Submitted
Eng. Ahmed Y. Asiri
Done2026-09-28
PM review
Eng. Ahmed Y. Asiri
Done2026-09-29
Impact analysis
Karim Haddad
Done2026-10-03
- 4
Board decision
Dr. Mohammed I. Al-Subaie
Now2026-10-29
- 5
Sponsor sign-off
Eng. Turki A. Al-Anazi
Later
- 6
Baseline updated
Eng. Ahmed Y. Asiri
Later
Board vote
Members vote before or during the session; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairNot voted
- Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
- Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saApprove
- Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saApprove
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saNot voted
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saApprove
- Approve4
- Approve with conditions0
- Reject0
- Abstain0
Quorum met · Awaiting the board’s decision in session 42