RSK-0034Buraydah Administrative Courts Complex
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Clay layers and voids under the southern part of the site that the initial soil tests missed
Preventive controls
- Extra soil tests at axes 12 to 16
- A change request to redesign the foundations
- Dewatering at axis 14
1 / 3
Event
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
Excavation stopped at any axis for more than 10 days
Contingency
Switch to deeper rotary-bored piles
Impact
Foundations of five axes redesigned, 55 days late, SAR 27M
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 27M
Residual
60% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director
Last reviewed 5 days ago
Project manager
Eng. Ahmed Y. Asiri
Currently followed up hereProgramme manager
Current levelEng. Ahmed Y. Asiri
Automatically at 15 days unreviewed · in 10 days- 3
EPMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 15 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the EPMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Extra soil tests at axes 12 to 16
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saDone2026-10-202026-10-209 Jumada I 1448 AHA change request to redesign the foundations
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saDone2026-09-282026-09-2817 Rabiʻ II 1448 AHDewatering at axis 14
Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)P-043a.alamoudi@bog.gov.saIn progressIn 11 days2026-11-0828 Jumada I 1448 AH
Trigger
Excavation stopped at any axis for more than 10 days
Contingency
Switch to deeper rotary-bored piles