CR-2026-002Northern Ring Road Development — Phase 2

Upgrade interchange 5 to a three-level interchange

ScopeApproved

Justification and the cost, schedule and risk impact, with a recommendation.

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 38.5M

Current budgetSAR 1.1B

After the changeSAR 1.2B

+3.4%

Schedule

+⁦60⁩ d
  • Baseline finish2027-05-01
  • New finish2027-06-30

Risk

+3
9Medium12Medium
Risk RSK-0017 · Contractor claim for a 120-day extension with compensation

Raises the chance of extension claims

Benefits

+9%

12 minutes off peak-hour journeys

⁦+9⁩% of expected benefits

Reason for change

An updated traffic study expects interchange 5 to exceed capacity within 5 years

Business justification

Building now costs about 60% less than rebuilding later and serves the Northern Logistics Zone

PMO recommendation

Approve with conditions

The PMO recommends approval with a fixed unit rate for the bridge works

Conditions

  • Fix the unit rate for bridge works

Approval workflow

  1. Submitted

    Eng. Ahmed Y. Asiri

    Done2026-03-02

  2. PM review

    Eng. Ahmed Y. Asiri

    Done2026-03-03

  3. Impact analysis

    Karim Haddad

    Done2026-03-07

  4. Board decision

    Dr. Mohammed I. Al-Subaie

    Done2026-03-22

  5. Sponsor sign-off

    Eng. Turki A. Al-Anazi

    Done2026-03-24

  6. Baseline updated

    Eng. Ahmed Y. Asiri

    Done2026-03-26

Board vote

Members vote before or during the session; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saApprove
  • Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the board on 22 March 2026The decision in the log · DEC-2026-009

Baseline

Baseline updated on 26 March 2026