RSK-0017Board of Grievances Headquarters, Riyadh
Contractor claim for a 120-day extension with compensation
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Approved variations with no matching time extension, and late handover of parts of the site
Preventive controls
- An independent time-impact analysis of the claim
1 / 1
Event
Contractor claim for a 120-day extension with compensation
The contractor rejects the independent analysis
Contingency
Refer the claim to the dispute resolution committee
Impact
A 120-day extension claim with compensation up to SAR 18.5M
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 18.5M
Residual
44% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director
Last reviewed 8 days ago
Project manager
Current levelEng. Ahmed Y. Asiri
Currently followed up here- 2
Programme manager
Eng. Ahmed Y. Asiri
Automatically at 15 days unreviewed · in 7 days - 3
EPMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 12 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the EPMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
An independent time-impact analysis of the claim
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@bog.gov.saIn progressIn 23 days2026-11-2010 Jumada II 1448 AH
Trigger
The contractor rejects the independent analysis
Contingency
Refer the claim to the dispute resolution committee