Original
Original baseline
- Finish
- 2027-06-30
- Budget
- SAR 1.1B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-03-03 · by Eng. Turki A. Al-Anazi
A 210,000 m² campus housing the headquarters and the Supreme Administrative Court in six linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Planned 51%
Estimate at completion
SAR +88.8M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control11 January 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-03-03 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Ahmed Y. Asiri
What changed from version A to version B
Finish
2027-06-302027-09-29
+91 days
Budget
SAR 1.1BSAR 1.2B
+38.50 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference