PRJ-2026-002Off track7ExecutionConstruction

Board of Grievances Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus housing the headquarters and the Supreme Administrative Court in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩

Planned ⁦51%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control11 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 September 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate8 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate11 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 1.2B split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 88.8M
EAC SAR 1.3B
Revised request SAR 1.2B
  • Actual spendSAR 532.9M
  • Committed, not spentSAR 563.5M
  • Allotted, uncommittedSAR 48.2M
  • Contingency availableSAR 35.4M

Budget

Original budgetwhen the first baseline was approved
SAR 1.1B
Approved budgetafter approved change requests
SAR 1.2B
Current budgetavailable to spend now
SAR 1.2B
Revised budgetif the pending changes are approved
SAR 1.2B

Commitments

Commitmentssigned contracts and purchase orders
SAR 1.1B
Contracts2 active contracts
SAR 1.1B
Purchase orders⁦0⁩ orders
SAR 11.1M
Remaining budgetapproved less actual
SAR 647.1M

Spend & outlook

Actual costincluding accruals
SAR 532.9M
Accrualswork done, not yet invoiced
SAR 21.3M
Estimate at completionthe PM’s bottom-up forecast
SAR 1.3B
ContingencySAR 23.6M drawn of SAR 59M
SAR 35.4M

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 23.6M drawn of SAR 59M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 23.6M

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance68.6876.2476.2476.24⁦−7.56⁩
2Design & permits137.35152.48152.48152.48⁦−15.12⁩
3Civil works434.95420.34304.19452.23⁦−17.28⁩
4MEP works343.38305.010.00388.76⁦−45.38⁩
5Handover160.24142.340.00181.42⁦−21.18⁩
Unallocated contingency35.400.000.0017.70⁦+17.70⁩
Total1,180.001,096.40532.901,268.82⁦−88.82⁩

Budget split

WBS

SAR 1.2B

Budget

  • Management & governanceSAR 68.7M⁦6%⁩
  • Design & permitsSAR 137.4M⁦12%⁩
  • Civil worksSAR 434.9M⁦37%⁩
  • MEP worksSAR 343.4M⁦29%⁩
  • HandoverSAR 160.2M⁦14%⁩
  • Unallocated contingencySAR 35.4M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2030-02-15⁩+961

SPI(t) ⁦0.56⁩ against the approved finish ⁦2027-06-30⁩

Planned valuePV
SAR 1.1B
The value of the work that should be done by today.
PV
Earned valueEV
SAR 495.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 532.9M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 1.2B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−37.30⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−561.68⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.93
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.47
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 1.3B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 735.9M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−88.82⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.06
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 1.3B
  • If the rest goes to planSAR 1.2B
  • At cost and schedule performanceSAR 2.1B
  • The PM’s bottom-up estimateSAR 1.3B
  • To stay within SAR 1.2B, cost performance on the rest must rise to ⁦1.06⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 1.3B

Variance at completion: ⁦−88.82⁩ SAR M