PRJ-2026-002Off track7ExecutionConstruction

Board of Grievances Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus housing the headquarters and the Supreme Administrative Court in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩

Planned ⁦51%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control11 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 September 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate3 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate8 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate11 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay228 days
Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27Oct 27
Contractual
Build completePlanned: ⁦2026-03-05⁩Forecast / actual: ⁦2027-01-17⁩Delay: 318 daysG3 +318
Executive
Project plan approvedPlanned: ⁦2024-11-09⁩Forecast / actual: ⁦2025-05-27⁩Delay: 199 daysG1 +199
Payment
Final handoverPlanned: ⁦2027-06-30⁩Forecast / actual: ⁦2027-09-29⁩Delay: 91 daysG5 +91
Regulatory
Testing & acceptance completePlanned: ⁦2026-12-19⁩Forecast / actual: ⁦2027-06-19⁩Delay: 182 daysG4 +182
Project
Designs approvedPlanned: ⁦2025-05-20⁩Forecast / actual: ⁦2026-05-07⁩Delay: 352 daysG2 +352

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2024-11-09⁩⁦2025-05-27⁩⁦+199⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-05-20⁩⁦2026-05-07⁩⁦+352⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-05⁩⁦2027-01-17⁩⁦+318⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-12-19⁩⁦2027-06-19⁩⁦+182⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-06-30⁩⁦2027-09-29⁩⁦+91⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline002-D1ApprovedEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saEng. Bandar M. Al-Shammari⁦2024-08-04⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting002-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2024-11-09⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design002-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-02-13⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals002-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-05-20⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation002-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-08-25⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure002-D6Under reviewEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-11-29⁩V1⁦1⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩