Programme · PG-07 · Infrastructure Portfolio

Regional Road Network Programme

Off track

Ring roads, bridges, mountain highways and logistics infrastructure.

Approved budget
SAR 2.3B

incl. SAR 40M programme reserve

Actual spend
SAR 784.9M

⁦34%⁩ of budget

EAC
SAR 2.4B+5.1%

Estimate at completion

Progress
⁦32%⁩

Planned ⁦39%⁩

Schedule performance index
0.87

Cost performance index 0.95

Manager

Eng. Ahmed Y. Asiri

Director General, Roads & Bridges

Sponsor

Eng. Bandar M. Al-Shammari

Deputy, Infrastructure

Projects

4 projects

2024-03-03 — 2028-12-31

On track 1At risk 1Off track 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Connect the region’s cities and governorates with a qualified road network

  2. 2

    Deliver 120 km of road a year to 2028

  3. 3

    Infrastructure ready for the northern logistics zone

Programme benefits

From baseline to target

  • Road length delivered this year

    by ⁦2026⁩
    Baseline 0Current 97 kmTarget 120
  • Population served by a qualified road network

    by ⁦2027⁩
    Baseline 71Current 76.4 %Target 78
  • Logistics investment attracted

    by ⁦2028⁩
    Baseline 0Current 610 SAR MTarget 900

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-09-12
2027-08-03
2027-09-28
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The bridge sits on the ring road’s phase-2 alignment

  • Critical

    The logistics zone is reached from the ring road

Shared risks

Risks that hit more than one project, managed at programme level.

20

Late land acquisition along the road and bridge alignment

PRK-07-1·Escalate·Eng. Ahmed Y. Asiri

Affects
12

Asphalt and steel shortages at the peak of the season

PRK-07-2·Mitigate·Eng. Ahmed Y. Asiri

Affects

Open risks in the programme’s projects

8 risks

Open risks in the programme’s projects
  • Critical3
  • High3
  • Medium2
  • Low0
  • Risks 8
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High1 · Critical0 · Critical
40 · Low0 · Medium0 · Medium2 · High2 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium1 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely5

Monitor0

Keep informed0

Eng. Bandar M. Al-ShammariManage closelyEng. Turki A. Al-AnaziManage closelyYousef A. Al-OmariManage closelyEng. Waleed O. Al-JuhaniManage closelyMunirah A. Al-KhalidiManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & Technology
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & TechnologySarah A. Al-Qarni · VP, Support Services
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Bid Evaluation & Award Committee

As needed · Quorum ⁦3⁩

Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistMazen A. Al-Hazmi · Procurement & Tendering SpecialistEng. Ibrahim A. Al-Ghamdi · Director, Engineering SupervisionEng. Asma S. Al-Hamdan · Enterprise Architect
Chair: Munirah A. Al-KhalidiNo meeting scheduled

Programme projects

The programme’s performance is computed from these projects (§6).

⁦4⁩ results
Export CSV
Manager
Northern Ring Road Development — Phase 2PRJ-2026-002Eng. Ahmed Y. Asiri7ExecutionOff track⁦42%⁩1.2B1.3B⁦+7.5%⁩0.82Schedule performance index · 0.820.93Cost performance index · 0.93
Wadi Al-Rummah BridgePRJ-2026-020Eng. Ahmed Y. Asiri7ExecutionOff track⁦44%⁩345M363.2M⁦+5.3%⁩0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Abha – Al-Baha Road DualisationPRJ-2026-021Eng. Ibrahim A. Al-Ghamdi6ProcurementOn track⁦2%⁩520M520M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Northern Logistics Zone InfrastructurePRJ-2026-034Eng. Ibrahim A. Al-Ghamdi7ExecutionAt risk⁦33%⁩238M247.9M⁦+4.2%⁩0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Total · 42.3B2.4B
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SAR 2.3B

Budget

  • Northern Ring Road Development — Phase 2SAR 1.2B⁦52%⁩
  • Wadi Al-Rummah BridgeSAR 345M⁦15%⁩
  • Abha – Al-Baha Road DualisationSAR 520M⁦23%⁩
  • Northern Logistics Zone InfrastructureSAR 238M⁦10%⁩
Budget shares
CategoryValueShare
Northern Ring Road Development — Phase 2SAR 1.2B⁦52%⁩
Wadi Al-Rummah BridgeSAR 345M⁦15%⁩
Abha – Al-Baha Road DualisationSAR 520M⁦23%⁩
Northern Logistics Zone InfrastructureSAR 238M⁦10%⁩
TotalSAR 2.3B⁦100%⁩