Late land acquisition along the road and bridge alignment
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Programme · PG-07 · Infrastructure Portfolio
Ring roads, bridges, mountain highways and logistics infrastructure.
incl. SAR 40M programme reserve
34% of budget
Estimate at completion
Planned 39%
Cost performance index 0.95
Manager
Eng. Ahmed Y. Asiri
Director General, Roads & Bridges
Sponsor
Eng. Bandar M. Al-Shammari
Deputy, Infrastructure
Projects
4 projects
2024-03-03 — 2028-12-31
On track 1At risk 1Off track 2
What the programme must achieve, and the strategic objectives it serves.
Connect the region’s cities and governorates with a qualified road network
Deliver 120 km of road a year to 2028
Infrastructure ready for the northern logistics zone
From baseline to target
Road length delivered this year
by 2026Population served by a qualified road network
by 2027Logistics investment attracted
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The bridge sits on the ring road’s phase-2 alignment
Critical
The logistics zone is reached from the ring road
Risks that hit more than one project, managed at programme level.
Late land acquisition along the road and bridge alignment
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Asphalt and steel shortages at the peak of the season
PRK-07-2·Mitigate·Eng. Ahmed Y. Asiri
8 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 1 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 2 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Road length delivered this year (cumulative)
97km
+9
Target 120km81%
Infrastructure projects delivered to plan
73%
+1
Target 85%86%
Population served by a qualified road network
76.4%
+1
Target 78.0%98%
Investment attracted (cumulative)
1,810SAR M
+230
Target 2,40075%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely5
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
As needed · Quorum 3
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Northern Ring Road Development — Phase 2PRJ-2026-002 | Eng. Ahmed Y. Asiri | 7Execution | Off track | 42% | 1.2B | 1.3B+7.5% | 0.82Schedule performance index · 0.82 | 0.93Cost performance index · 0.93 |
| Wadi Al-Rummah BridgePRJ-2026-020 | Eng. Ahmed Y. Asiri | 7Execution | Off track | 44% | 345M | 363.2M+5.3% | 0.80Schedule performance index · 0.80 | 0.95Cost performance index · 0.95 |
| Abha – Al-Baha Road DualisationPRJ-2026-021 | Eng. Ibrahim A. Al-Ghamdi | 6Procurement | On track | 2% | 520M | 520M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Northern Logistics Zone InfrastructurePRJ-2026-034 | Eng. Ibrahim A. Al-Ghamdi | 7Execution | At risk | 33% | 238M | 247.9M+4.2% | 0.89Schedule performance index · 0.89 | 0.96Cost performance index · 0.96 |
| Total · 4 | 2.3B | 2.4B |
SAR 2.3B
Budget
| Category | Value | Share |
|---|---|---|
| Northern Ring Road Development — Phase 2 | SAR 1.2B | 52% |
| Wadi Al-Rummah Bridge | SAR 345M | 15% |
| Abha – Al-Baha Road Dualisation | SAR 520M | 23% |
| Northern Logistics Zone Infrastructure | SAR 238M | 10% |
| Total | SAR 2.3B | 100% |