The objective’s weakest KPI, “Road length delivered this year (cumulative)”, is at 81% of its target, and its heaviest project, “Northern Ring Road Development — Phase 2”, is Off track. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up land acquisition with the municipality and the valuation committee
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010·t.alanazi@alwaha.gov.saDue 2026-10-208 days overdue2026-10-20·9 Jumada I 1448 AHK-1.1.1Northern Ring Road Development — Phase 2
Overdue
Split the lighting works out of the Northern Ring Road contract and tender them separately
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020·a.asiri@alwaha.gov.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHK-1.1.1Northern Ring Road Development — Phase 2
In progress
An extra night shift on Wadi Al-Rummah Bridge until year end
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036·i.alghamdi@alwaha.gov.saDue 2026-12-31In 64 days2026-12-31·22 Rajab 1448 AHK-1.1.2Wadi Al-Rummah Bridge
In progress
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
Slow land acquisition on the northern alignment has held Ring Road phase 2 back by about four months.
Eng. Ahmed Y. Asiri · 2026-10-12
Challenge
Steel and asphalt prices have pushed up the forecast cost of Wadi Al-Rummah Bridge.
Eng. Ibrahim A. Al-Ghamdi · 2026-09-28
Note
The steering committee advised splitting the lighting works out of the ring-road contract to speed delivery.