Build integrated infrastructure connecting the region’s cities and governorates

At riskSustainable Regional Development

Complete the regional road network, bridges and utilities that enable growth.

⁦74%⁩

Attainment

of the ⁦85%⁩ target

Attainment through 2026

Weight in pillar

⁦40%⁩

Sustainable Regional Development

KPI status

3

  • On track1
  • At risk1
  • Off track1

Linked investment

SAR 2.2B

5 projects

Attainment through 2026

The objective’s monthly attainment against this year’s target.

Attainment through 2026
Attainment through 2026
PeriodAttainment
Jan⁦63.6%⁩
Feb⁦63.8%⁩
Mar⁦65.7%⁩
Apr⁦66.2%⁩
May⁦68.3%⁩
Jun⁦69.3%⁩
Jul⁦70.0%⁩
Aug⁦71.7%⁩
Sep⁦72.8%⁩
Oct⁦74.0%⁩

KPIs

Baseline, target and actual for each KPI, and progress from baseline to target.

Sub-objectives

Their weights inside the objective and their progress; the weighted sum is the objective’s attainment.

  • Finish the ring roads and main corridors

    OBJ-01.1

    Weight

    ⁦50%⁩

    ⁦70%⁩Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa
  • Build bridges and free-flow junctions

    OBJ-01.2

    Weight

    ⁦30%⁩

    ⁦72%⁩Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.sa
  • Link the governorates with safe dual carriageways

    OBJ-01.3

    Weight

    ⁦20%⁩

    ⁦89%⁩Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa

Contributing initiatives & projects

The objective’s approved initiatives and their projects, and each project’s share of the contribution by investment.

Initiative · SI-1.1.1

Complete the regional road network

Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa2BOff track

Projects contributing from other objectives’ initiatives

Corrective actions

What we are doing to bring the KPI back on track, who owns it, and by when.

  • Speed up land acquisition with the municipality and the valuation committee

    Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziVP, Projects & InfrastructureP-010t.alanazi@alwaha.gov.saDue ⁦2026-10-20⁩8 days overdue2026-10-209 Jumada I 1448 AHK-1.1.1Northern Ring Road Development — Phase 2
    Overdue
  • Split the lighting works out of the Northern Ring Road contract and tender them separately

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.saDue ⁦2026-11-30⁩In 33 days2026-11-3020 Jumada II 1448 AHK-1.1.1Northern Ring Road Development — Phase 2
    In progress
  • An extra night shift on Wadi Al-Rummah Bridge until year end

    Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saDue ⁦2026-12-31⁩In 64 days2026-12-3122 Rajab 1448 AHK-1.1.2Wadi Al-Rummah Bridge
    In progress

Challenges & notes

What holds the objective back and what leadership should know.

  • Challenge

    Slow land acquisition on the northern alignment has held Ring Road phase 2 back by about four months.

    Eng. Ahmed Y. Asiri · 2026-10-12

  • Challenge

    Steel and asphalt prices have pushed up the forecast cost of Wadi Al-Rummah Bridge.

    Eng. Ibrahim A. Al-Ghamdi · 2026-09-28

  • Note

    The steering committee advised splitting the lighting works out of the ring-road contract to speed delivery.

    Eng. Turki A. Al-Anazi · 2026-10-05