AI insight
52% chance of a further slip within 45 days
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
640 km of fibre linking government buildings and smart-city assets.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 63%
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
81
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 55% done against 63% planned.
SPI 0.87, CPI 0.97.
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 89% of budget
0 approvals and 0 open actions on this project
From «My actions» for this project
0 open
Cost and schedule impact
2 open risks, exposure SAR 6.1M
Impact
2 of 4 approved
1 member