Secure Judicial Network
Add to watchlist640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 63%
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SAR 132M split into spent, committed and left, with the estimate at completion
- Actual spendSAR 74.8M
- Committed, not spentSAR 43.2M
- Allotted, uncommittedSAR 10M
- Contingency availableSAR 4M
Budget
- Original budgetwhen the first baseline was approved
- SAR 132M
- Approved budgetafter approved change requests
- SAR 132M
- Current budgetavailable to spend now
- SAR 132M
- Revised budgetif the pending changes are approved
- SAR 133.2M
Commitments
- Commitmentssigned contracts and purchase orders
- SAR 118M
- Contracts1 active contract
- SAR 108M
- Purchase orders0 orders
- SAR 10M
- Remaining budgetapproved less actual
- SAR 57.2M
Spend & outlook
- Actual costincluding accruals
- SAR 74.8M
- Accrualswork done, not yet invoiced
- SAR 3M
- Estimate at completionthe PM’s bottom-up forecast
- SAR 136.1M
- ContingencySAR 2.6M drawn of SAR 6.6M
- SAR 4M
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SAR 2.6M drawn of SAR 6.6M
- Covering realised delivery risks2026-08-29SAR 2.6M
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSAR M | CommittedSAR M | ActualSAR M | EACSAR M | VarianceSAR M | Consumption |
|---|---|---|---|---|---|---|
| 1Management & governance | 7.68 | 8.17 | 8.17 | 8.17 | −0.48 | |
| 2Design & permits | 15.36 | 16.33 | 16.33 | 16.33 | −0.97 | |
| 3Civil works | 48.66 | 50.34 | 50.34 | 50.34 | −1.69 | |
| 4MEP works | 38.41 | 29.42 | 0.00 | 40.40 | −1.99 | |
| 5Handover | 17.93 | 13.73 | 0.00 | 18.86 | −0.93 | |
| Unallocated contingency | 3.96 | 0.00 | 0.00 | 1.98 | +1.98 | |
| Total | 132.00 | 118.00 | 74.85 | 136.08 | −4.08 |
Budget split
WBS
SAR 132M
Budget
- Management & governanceSAR 7.7M6%
- Design & permitsSAR 15.4M12%
- Civil worksSAR 48.7M37%
- MEP worksSAR 38.4M29%
- HandoverSAR 17.9M14%
- Unallocated contingencySAR 4M3%
Cash flow
Planned, committed, actual and forecast
Spend per period
SAR millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
- Forecast
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
0.58
Off track
Schedule performance index
SPI = EV ÷ PV
0.97
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2028-02-17+382
SPI(t) 0.62 against the approved finish 2027-01-31
- Planned valuePV
- SAR 124.7M
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SAR 72.6M
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SAR 74.8M
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SAR 132M
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- −2.25 SAR M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- −52.09 SAR M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 0.97
- Value produced per riyal spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 0.58
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SAR 136.1M
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SAR 61.2M
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- −4.08 SAR M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 1.04
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSAR 136.1M
- If the rest goes to planSAR 134.2M
- At cost and schedule performanceSAR 180M
- The PM’s bottom-up estimateSAR 136.1M
- To stay within SAR 132M, cost performance on the rest must rise to 1.04 — above what has been achieved.
Estimate at completion at that performance
SAR 136.1M
Variance at completion: −4.08 SAR M