PRJ-2026-018At risk7ExecutionConstruction
Secure Judicial Network
Add to watchlist640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.
Early warning: 52% chance of slipping within 45 days
Budget (BAC)
SAR 132M
Actual cost
SAR 74.8M
57% of budget
Progress
55%
Planned 63%
Estimate at completion
SAR 136.1M
SAR +4.1M
SPI · CPI
0.87Schedule performance index · 0.870.97Cost performance index · 0.97
Forecast finish
2027-03-05
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work128M17 elements
Unallocated contingency4MSAR 6.6M
Budget at completion132MPRJ-2026-018
Weighted progress55%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total55%128.0474.85