PRJ-2026-018At risk7ExecutionConstruction

Secure Judicial Network

Add to watchlist

640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+29⁩ days vs approved

Original baseline⁦2027-01-31⁩
Approved baseline⁦2027-01-31⁩
Current forecast⁦2027-03-01⁩
By earned schedule⁦2028-02-17⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.58
earned ÷ planned value
Next milestone
in 14 days
Build complete
Expand allCollapse all
Activity
Secure Judicial NetworkPlanned: ⁦2025-05-11⁩ → ⁦2027-01-31⁩Forecast: ⁦2025-05-11⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-05-11⁩ → ⁦2025-09-18⁩Actual: ⁦2025-05-11⁩ → ⁦2025-12-08⁩
Project plan & baselinePlanned: ⁦2025-05-11⁩ → ⁦2025-07-30⁩Actual: ⁦2025-05-11⁩ → ⁦2025-09-18⁩
Monitoring & reportingPlanned: ⁦2025-06-30⁩ → ⁦2025-09-18⁩Actual: ⁦2025-07-31⁩ → ⁦2025-12-08⁩
Project plan approvedPlanned: ⁦2025-09-18⁩ → ⁦2025-09-18⁩Actual: ⁦2025-12-08⁩ → ⁦2025-12-08⁩Project plan approved
Design & permitsPlanned: ⁦2025-08-19⁩ → ⁦2025-12-27⁩Actual: ⁦2025-10-20⁩ → ⁦2026-05-19⁩
Detailed designPlanned: ⁦2025-08-19⁩ → ⁦2025-11-07⁩Actual: ⁦2025-10-20⁩ → ⁦2026-02-27⁩
Permits & approvalsPlanned: ⁦2025-10-08⁩ → ⁦2025-12-27⁩Actual: ⁦2026-01-09⁩ → ⁦2026-05-19⁩
Designs approvedPlanned: ⁦2025-12-27⁩ → ⁦2025-12-27⁩Actual: ⁦2026-05-19⁩ → ⁦2026-05-19⁩Designs approved
Civil worksPlanned: ⁦2025-11-27⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-03-07⁩ → ⁦2026-11-11⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2025-11-27⁩ → ⁦2026-02-15⁩Actual: ⁦2026-03-31⁩ → ⁦2026-08-08⁩
StructurePlanned: ⁦2026-01-16⁩ → ⁦2026-04-06⁩Actual: ⁦2026-06-20⁩ → ⁦2026-10-26⁩
FinishesPlanned: ⁦2026-03-07⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-03-07⁩ → ⁦2026-11-11⁩Float: ⁦0⁩d+169
Build completePlanned: ⁦2026-05-26⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-11-11⁩ → ⁦2026-11-11⁩Float: ⁦110⁩dBuild complete
MEP worksPlanned: ⁦2026-04-26⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-10-28⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-04-26⁩ → ⁦2026-07-15⁩Forecast: ⁦2026-10-28⁩ → ⁦2026-12-03⁩Float: ⁦0⁩d+141
InstallationPlanned: ⁦2026-06-15⁩ → ⁦2026-09-03⁩Forecast: ⁦2026-11-19⁩ → ⁦2026-12-25⁩Float: ⁦0⁩d+113
Testing & commissioningPlanned: ⁦2026-08-04⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-12-11⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d+85
Testing & acceptance completePlanned: ⁦2026-10-23⁩ → ⁦2026-10-23⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦44⁩dTesting & acceptance complete
HandoverPlanned: ⁦2026-09-23⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-09-23⁩ → ⁦2026-12-12⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-02-07⁩Float: ⁦0⁩d+57
Final acceptancePlanned: ⁦2026-11-12⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-01-24⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d+29
Final handoverPlanned: ⁦2027-01-31⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-03-01⁩ → ⁦2027-03-01⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 101 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

81
143
169
85
29
G1G2G3G4G5

The critical chain