Secure Judicial Network
Add to watchlist640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 63%
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-18 | 2025-12-08 | +81 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-27 | 2026-05-19 | +143 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-26 | 2026-11-11 | +169 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-23 | 2027-01-16 | +85 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-01-31 | 2027-03-01 | +29 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline018-D1 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-07-30 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting018-D2 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-09-18 | V1 | 2 of 2 |
| Deliverable: Detailed design018-D3 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-11-07 | V1 | 2 of 2 |
| Deliverable: Permits & approvals018-D4 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2025-12-27 | V1 | 2 of 2 |
| Deliverable: Site works & excavation018-D5 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-02-15 | V1 | 2 of 2 |
| Deliverable: Structure018-D6 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Nayef H. Al-Buqami | 2026-04-06 | V1 | 2 of 2 |