Original
Original baseline
- Finish
- 2027-01-31
- Budget
- SAR 132M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Majed S. Al-Rasheed
640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 63%
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Majed S. Al-Rasheed
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Omar H. Bawazir
What changed from version A to version B
Finish
2027-01-312027-03-01
+29 days
Budget
SAR 132MSAR 133.2M
+1.20 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference