Excavation permits delay fibre and everything on it
PRK-08-1·Mitigate·Eng. Omar H. Bawazir
Programme · PG-08 · Infrastructure Portfolio
Smart lighting, fibre, traffic monitoring and the integrated operations centre.
incl. SAR 10M programme reserve
37% of budget
Estimate at completion
Planned 42%
Cost performance index 0.97
Manager
Eng. Omar H. Bawazir
Director, IT Infrastructure
Sponsor
Eng. Majed S. Al-Rasheed
VP, Digital Transformation & Technology
Projects
4 projects
2025-02-16 — 2028-12-31
On track 2At risk 2
What the programme must achieve, and the strategic objectives it serves.
An integrated operations centre that sees the city in real time
Cut public-lighting energy by 45%
Fibre to every government building
From baseline to target
Lighting energy reduction
by 2027Buildings on fibre
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Smart poles connect over the fibre network
Critical
Traffic cameras need fibre
The operations centre takes the traffic feeds
Lighting is run from the operations centre
Risks that hit more than one project, managed at programme level.
Excavation permits delay fibre and everything on it
PRK-08-1·Mitigate·Eng. Omar H. Bawazir
5 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 0 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 1 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Resident satisfaction with the urban landscape
71%
+1
Target 72%99%
Population served by a qualified road network
76.4%
+1
Target 78.0%98%
Carbon emissions cut against baseline
9.7%
+1
Target 12.0%81%
Systems hosted on the government cloud
47%
+2
Target 50%94%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Smart Street LightingPRJ-2026-013 | Eng. Waleed O. Al-Juhani | 7Execution | At risk | 79% | 74M | 78.7M+6.4% | 0.88Schedule performance index · 0.88 | 0.94Cost performance index · 0.94 |
| Fibre Optic Network ExpansionPRJ-2026-018 | Eng. Omar H. Bawazir | 7Execution | At risk | 55% | 132M | 136.1M+3.1% | 0.87Schedule performance index · 0.87 | 0.97Cost performance index · 0.97 |
| Intelligent Traffic Monitoring SystemPRJ-2026-022 | Eng. Yasser M. Al-Zahrani | 5Approval | On track | 2% | 46M | 46M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Smart City Integrated Operations CentrePRJ-2026-024 | Eng. Omar H. Bawazir | 2Feasibility | On track | 0% | 110M | 110M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 4 | 362M | 370.8M |
SAR 362M
Budget
| Category | Value | Share |
|---|---|---|
| Smart Street Lighting | SAR 74M | 20% |
| Fibre Optic Network Expansion | SAR 132M | 36% |
| Intelligent Traffic Monitoring System | SAR 46M | 13% |
| Smart City Integrated Operations Centre | SAR 110M | 30% |
| Total | SAR 362M | 100% |