Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-018At risk7ExecutionConstruction

Secure Judicial Network

Add to watchlist

640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Scope statement

What the project delivers, what it does not, and when a deliverable counts as accepted.

⁦640⁩ km of fibre and backup links connecting ⁦46⁩ judicial sites to the Board’s secure network.

In scope

  • ⁦640⁩ km of fibre and backup links connecting ⁦46⁩ judicial sites to the Board’s secure network.
  • Saudi Building Code compliance
  • An approved plan to keep the courts sitting during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the business owner
  • Main deliverable — final stageMeets the approved specification, signed off by the business owner

Scope baseline

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-06-09⁩

    Baseline approved at the planning gate

    Budget132MFinish⁦2027-01-31⁩

Requirements register

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical1
  • Regulatory2
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦50%⁩

3/6 · test result is a pass

Accepted

⁦50%⁩

3/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-018-01Reach the target number of courtroomsBusinessMustIn progressEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.saSB-1
REQ-018-02Meet the approved technical specsTechnicalMustIn progressEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.saSB-1
REQ-018-03Courts keep sitting during the worksFunctionalMustIn progressEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.saSB-1
REQ-018-04Saudi Building CodeRegulatoryCouldApprovedEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.saSB-1
REQ-018-05Civil-defence requirementsRegulatoryCouldApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@bog.gov.saSB-1
REQ-018-06Site and systems securitySecurityShouldIn progressEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrix

Requirement → deliverable → task → test → acceptance. No requirement has a gap.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close