Secure Judicial Network
Add to watchlist640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Planned 63%
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started