PRJ-2026-018At risk7ExecutionConstruction

Secure Judicial Network

Add to watchlist

640 km of fibre and backup links connecting 46 judicial sites to the Board’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate22 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate12 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate30 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started