Board of Grievances Headquarters, Riyadh
Remove from watchlistA 210,000 m² campus housing the headquarters and the Supreme Administrative Court in six linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Planned 51%
Estimate at completion
SAR +88.8M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control11 January 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 September 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 May 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate8 June 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate11 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth