Board of Grievances Headquarters, Riyadh
Remove from watchlistA 210,000 m² campus housing the headquarters and the Supreme Administrative Court in six linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Planned 51%
Estimate at completion
SAR +88.8M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control11 January 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 September 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate3 May 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate8 June 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate11 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+91 days vs approved
- Critical activities
- 7
- of 10 open activities
- Late activities
- 7
- past their baseline finish
- Schedule performance
- 0.47
- earned ÷ planned value
- Next milestone
- in 81 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 10 open activities, data date 2026-10-28
“Structure” needs a pace 3.5× faster than it has kept
It earned 89% in 487 days; the forecast assumes the rest in 17 days. At the pace so far it finishes on 2026-12-27.
Milestones slip 263 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance
Near-critical