CR-2026-001Unified Digital Services Platform

Add a Nafath for Business integration

ScopeApproved

Justification and the cost, schedule and risk impact, with a recommendation.

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 2.4M

Current budgetSAR 84M

After the changeSAR 86.4M

+2.9%

Schedule

+⁦18⁩ d
  • Baseline finish2027-03-13
  • New finish2027-03-31

Risk

+4
12Medium16High
Risk RSK-0001 · Nafath and SADAD integration interfaces not ready on time

Adds more dependence on NIC interfaces

Benefits

+18%

Lifts digital transactions from 60% to 85%

⁦+18⁩% of expected benefits

Reason for change

The investment sector asked for the services to be open to businesses through Nafath for Business

Business justification

40% of licensing transactions are filed by businesses; without Nafath for Business they stay on paper

PMO recommendation

Approve

The PMO recommends approval: the benefit clearly outweighs the cost

Approval workflow

  1. Submitted

    Eng. Sultan F. Al-Ghamdi

    Done2026-02-10

  2. PM review

    Eng. Sultan F. Al-Ghamdi

    Done2026-02-11

  3. Impact analysis

    Karim Haddad

    Done2026-02-15

  4. Board decision

    Dr. Mohammed I. Al-Subaie

    Done2026-02-23

  5. Sponsor sign-off

    Eng. Majed S. Al-Rasheed

    Done2026-02-25

  6. Baseline updated

    Eng. Sultan F. Al-Ghamdi

    Done2026-02-27

Board vote

Members vote before or during the session; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saApprove
  • Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saAbstain
6/6Quorum met
  • Approve5
  • Approve with conditions0
  • Reject0
  • Abstain1

Decided by the board on 23 February 2026The decision in the log · DEC-2026-007

Baseline

Baseline updated on 27 February 2026