PRJ-2026-014At risk7ExecutionHybrid

Unified Digital Services Platform

Remove from watchlist

One platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩

Planned ⁦67%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control15 February 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Superseded
    Finish
    ⁦2027-03-13⁩
    ⁦−18⁩ days
    Budget
    SAR 84M
    ⁦53⁩ activities

    Approved at the planning gate with the original SAR 84.0M budget and a March 2027 launch.

    Approved ⁦2025-02-16⁩ · by Dr. Noura M. Al-Otaibi · via G3

  2. Approved revised

    Approved revised baseline

    v2.0Approved & lockedVersion A
    Finish
    ⁦2027-03-31⁩
    Budget
    SAR 86.4M
    ⁦56⁩ activities

    CR-2026-001 added Nafath for Business: SAR 2.4M and 18 days on the critical path.

    Approved ⁦2026-02-24⁩ · by Dr. Noura M. Al-Otaibi · via CR-2026-001

  3. Working

    Working baseline

    v3.0-draftWorking draftVersion B
    Finish
    ⁦2027-05-12⁩
    ⁦+42⁩ days
    Budget
    SAR 90.4M
    ⁦56⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Sultan F. Al-Ghamdi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-03-31⁩⁦2027-05-12⁩

⁦+42⁩ days

Budget

SAR 86.4MSAR 90.4M

⁦+3.98⁩ SAR M

Milestones moved

11 / 12

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-01
  • Charter approved
  • Build & run contract signed⁦+4⁩
  • Advance payment (10%) released⁦+7⁩
  • Requirements & design signed off⁦+21⁩
  • Internal pilot (MVP) live⁦+28⁩
  • Data classification approved by the data office⁦+14⁩
  • Wave 1 development complete (24 services)⁦+43⁩
  • Nafath & SADAD integration complete⁦+40⁩
  • Penetration test passed, security sign-off⁦+44⁩
  • User acceptance testing complete⁦+42⁩
  • Official platform launch⁦+45⁩
  • Final acceptance & final payment⁦+42⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Project management & governance⁦+0.25⁩
  • 2Requirements & service design⁦+0.20⁩
  • 3Core platform build⁦+1.09⁩
  • 4National systems integration⁦+1.53⁩
  • 5Data migration⁦+0.91⁩
  • 6Testing, quality & security⁦+0.83⁩
  • 7Launch & change management⁦+0.94⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev3.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Sultan F. Al-Ghamdi
  2. Recovery-plan snapshotv2.1-snapshotArchivedThe forecast shown to the Steering Committee with the recovery plan, before the two integration engineers left.⁦2026-09-15⁩by Eng. Sultan F. Al-Ghamdi
  3. Approved revised baselinev2.0Approved & lockedCR-2026-001 added Nafath for Business: SAR 2.4M and 18 days on the critical path.⁦2026-02-24⁩by Dr. Noura M. Al-Otaibi
  4. Post-award snapshotv1.1ArchivedReference snapshot after signature: the vendor’s detailed activity dates, totals unchanged.⁦2025-05-12⁩by Eng. Sultan F. Al-Ghamdi
  5. Original baselinev1.0SupersededApproved at the planning gate with the original SAR 84.0M budget and a March 2027 launch.⁦2025-02-16⁩by Dr. Noura M. Al-Otaibi