PRJ-2026-014At risk7ExecutionHybrid
Unified Digital Services Platform
Remove from watchlistOne platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.
Project managerEng. Sultan F. Al-GhamdiSponsorEng. Majed S. Al-RasheedProgrammeDigital Government Services Programme
Early warning: 74% chance of slipping within 45 days
Budget (BAC)
SAR 86.4M
Actual cost
SAR 52.2M
60% of budget
Progress
58%
Planned 67%
Estimate at completion
SAR 90M
SAR +3.6M
SPI · CPI
0.87Schedule performance index · 0.870.96Cost performance index · 0.96
Forecast finish
2027-05-12
42 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control15 February 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work84.3M67 elements
Unallocated contingency2.1MSAR 3.2M
Budget at completion86.4MPRJ-2026-014
Weighted progress58%Linked deliverables: 11
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total58%84.3052.20