Unified Digital Services Platform
Remove from watchlistOne platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.
Budget (BAC)
Actual cost
60% of budget
Progress
Planned 67%
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control15 February 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SAR 86.4M split into spent, committed and left, with the estimate at completion
- Actual spendSAR 52.2M
- Committed, not spentSAR 19.6M
- Allotted, uncommittedSAR 12.5M
- Contingency availableSAR 2.1M
Budget
- Original budgetwhen the first baseline was approved
- SAR 84M
- Approved budgetafter approved change requests
- SAR 86.4M
- Current budgetavailable to spend now
- SAR 86.4M
- Revised budgetif the pending changes are approved
- SAR 90.4M
Commitments
- Commitmentssigned contracts and purchase orders
- SAR 71.8M
- Contracts3 active contracts
- SAR 65.6M
- Purchase orders3 orders
- SAR 6.2M
- Remaining budgetapproved less actual
- SAR 34.2M
Spend & outlook
- Actual costincluding accruals
- SAR 52.2M
- Accrualswork done, not yet invoiced
- SAR 2.4M
- Estimate at completionthe PM’s bottom-up forecast
- SAR 90M
- ContingencySAR 1.1M drawn of SAR 3.2M
- SAR 2.1M
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SAR 1.1M drawn of SAR 3.2M
- Nafath integration — extra test environment2026-03-18SAR 420K
- Excavation permits — GIS integration need2026-06-09SAR 380K
- Data migration — cleansing establishment records2026-09-22SAR 300K
Purchase orders
- PO-2025-0118PMO advisory — first six monthsSAR 1.2MSAR 1.2M paid
- PO-2025-0634Identity & access management licencesSAR 2.6MSAR 2.6M paid
- PO-2026-0812Security & application scanning toolsSAR 2.4MSAR 800K paid
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSAR M | CommittedSAR M | ActualSAR M | EACSAR M | VarianceSAR M | Consumption |
|---|---|---|---|---|---|---|
| 1Project management & governance | 6.74 | 6.03 | 4.92 | 6.99 | −0.25 | |
| 2Requirements & service design | 10.12 | 10.31 | 10.31 | 10.31 | −0.20 | |
| 3Core platform build | 25.29 | 23.26 | 20.13 | 26.00 | −0.71 | |
| 4National systems integration | 15.17 | 12.01 | 7.11 | 16.29 | −1.11 | |
| 5Data migration | 8.43 | 6.70 | 4.03 | 9.04 | −0.61 | |
| 6Testing, quality & security | 10.12 | 7.74 | 4.08 | 10.95 | −0.83 | |
| 7Launch & change management | 8.43 | 5.75 | 1.61 | 9.37 | −0.94 | |
| Unallocated contingency | 2.10 | 0.00 | 0.00 | 1.05 | +1.05 | |
| Total | 86.40 | 71.80 | 52.20 | 90.00 | −3.60 |
Budget split
WBS
SAR 86.4M
Budget
- Project management & governanceSAR 6.7M8%
- Requirements & service designSAR 10.1M12%
- Core platform buildSAR 25.3M29%
- National systems integrationSAR 15.2M18%
- Data migrationSAR 8.4M10%
- Testing, quality & securitySAR 10.1M12%
- Launch & change managementSAR 8.4M10%
- Unallocated contingencySAR 2.1M2%
Cash flow
Planned, committed, actual and forecast
Spend per period
SAR millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
- Forecast
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
0.87
Off track
Schedule performance index
SPI = EV ÷ PV
0.96
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2027-06-27+88
SPI(t) 0.90 against the approved finish 2027-03-31
- Planned valuePV
- SAR 57.9M
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SAR 50.1M
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SAR 52.2M
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SAR 86.4M
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- −2.09 SAR M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- −7.78 SAR M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 0.96
- Value produced per riyal spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 0.87
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SAR 90M
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SAR 37.8M
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- −3.60 SAR M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 1.06
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSAR 90M
- If the rest goes to planSAR 88.5M
- At cost and schedule performanceSAR 95.9M
- The PM’s bottom-up estimateSAR 90M
- To stay within SAR 86.4M, cost performance on the rest must rise to 1.06 — above what has been achieved.
Estimate at completion at that performance
SAR 90M
Variance at completion: −3.60 SAR M