PRJ-2026-014At risk7ExecutionHybrid

Unified Digital Services Platform

Remove from watchlist

One platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩

Planned ⁦67%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control15 February 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

15 members, about ⁦6.3⁩ full-time equivalents

Leadership

3 members

  • Eng. Sultan F. Al-GhamdiProject manager⁦100%⁩Allocated ⁦115%⁩ across all projectsA
  • Eng. Reem K. Al-DosariProgramme manager (oversight)⁦20%⁩C
  • Eng. Majed S. Al-RasheedProject sponsor⁦20%⁩R

Core team

4 members

  • Hussam T. Al-QurashiLead integration engineer⁦100%⁩Allocated ⁦135%⁩ across all projectsR
  • Lama S. Al-HarbiSenior business analyst⁦80%⁩Allocated ⁦120%⁩ across all projectsR
  • Joud N. Al-AhmadiQA & test lead⁦70%⁩Allocated ⁦110%⁩ across all projectsR
  • Nouf M. Al-BalawiChange management specialist⁦30%⁩R

Specialists

5 members

  • Eng. Asma S. Al-HamdanEnterprise architect⁦30%⁩C
  • Rakan F. Al-MohammadiData engineer (migration)⁦30%⁩R
  • Khalid N. Al-MutairiFinance & contracts officer⁦20%⁩I
  • Eng. Yasser M. Al-ZahraniCybersecurity lead⁦15%⁩C
  • Eng. Saad M. Al-DosariCloud & integration engineer⁦15%⁩R

Vendor team & advisers

3 members

  • Maha F. Al-KhathamiFront-end developer⁦40%⁩R
  • Karim HaddadDigital delivery adviser⁦30%⁩C
  • Eng. Laila MansourArchitecture & integration adviser⁦25%⁩C
  • Open seatIntegration engineer (vendor) — since 11 October
  • Open seatIntegration engineer (vendor) — since 11 October

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦12⁩ stakeholders, ⁦8⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied3

high power, lower interest

Manage closely7

high power and interest

Monitor0

minimal effort

Keep informed2

high interest, lower power

Eng. Majed Al-RasheedManage closelyEng. Abdullah Al-QahtaniManage closelyDigital Government AuthorityManage closelyNational Information Center (Nafath)Keep satisfiedYousef Al-OmariManage closelyEng. Ahmed AsiriManage closelyService-centre staffKeep informedIndividual and business beneficiariesManage closelyDigital Solutions GroupKeep informedNational Cybersecurity AuthorityKeep satisfiedMunirah Al-KhalidiManage closelyLegal DepartmentKeep satisfied

Interest

VP Digital — project sponsor

Eng. Majed Al-Rasheed

Sponsor — decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Supportive

Now

Leading

At the level needed.

Impact on the project
Approves gates and major changes
Engagement plan
Monthly briefing, direct escalation within ⁦48⁩ h
Last contact⁦2026-10-21⁩
⁦12⁩ results
Export CSV
OrganisationRoleActions
Eng. Majed Al-RasheedVP Digital — project sponsorSponsor — decisions and fundingLeadingEng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa⁦2026-10-21⁩
Eng. Abdullah Al-QahtaniChief Executive OfficerSteering Committee chairSupportiveLeadingEng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesP-004r.aldosari@alwaha.gov.sa⁦2026-09-15⁩
Digital Government AuthorityRegulatorDigital services regulatorNeutralSupportiveLama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystP-006l.alharbi@alwaha.gov.sa⁦2026-10-27⁩
National Information Center (Nafath)Integration partnerNational identity providerNeutralSupportiveHussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@alwaha.gov.sa⁦2026-10-26⁩
Yousef Al-OmariInvestment Agency — licensing process ownerLicensing process ownerSupportiveLeadingLama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystP-006l.alharbi@alwaha.gov.sa⁦2026-10-23⁩
National Cybersecurity AuthorityRegulatorCybersecurity regulatorNeutralSupportiveEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@alwaha.gov.sa⁦2026-09-02⁩
Munirah Al-KhalidiFinancial Affairs AgencyApproves payments and certificatesSupportiveKhalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.sa⁦2026-10-12⁩
Eng. Ahmed AsiriRoads & Bridges — excavation-permit ownerExcavation-permit ownerResistantSupportiveEng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesP-004r.aldosari@alwaha.gov.sa⁦2026-10-08⁩
Individual and business beneficiariesBeneficiariesEnd beneficiariesNeutralSupportiveLama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystP-006l.alharbi@alwaha.gov.sa⁦2026-10-14⁩
Digital Solutions GroupMain vendorMain build & run vendorSupportiveEng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa⁦2026-10-26⁩
⁦1⁩–⁦10⁩ of ⁦12⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Steering CommitteeOverall status, variances, decisions neededMonthlyMeetingEng. Sultan F. Al-Ghamdi⁦2026-11-17⁩
  • Project sponsorWeekly status and top five risksWeeklyReportEng. Sultan F. Al-Ghamdi⁦2026-11-01⁩
  • Change Control BoardChange requests and impact analysisWeeklyMeetingEng. Sultan F. Al-Ghamdi⁦2026-10-29⁩
  • Process-owning departmentsPending requirements and sprint demosFortnightlyWorkshopLama S. Al-Harbi⁦2026-10-30⁩
  • Digital Government AuthorityRelease plan and compliance test resultsAt milestonesFormal letterLama S. Al-Harbi⁦2026-11-12⁩
  • National Information Center (Nafath)Environment readiness and integration issuesWeeklyMeetingHussam T. Al-Qurashi⁦2026-11-02⁩Overdue
  • Service-centre staffWhat changes in their work, training datesMonthlyNewsletterNouf M. Al-Balawi⁦2026-11-05⁩
  • BeneficiariesNew services and launch datesAt milestonesSMSNouf M. Al-BalawiAt launch
  • Main vendorActions due and performance against contractWeeklyMeetingEng. Sultan F. Al-Ghamdi⁦2026-11-02⁩
  • Leadership and watchersPerformance and early warningsDailyDashboardDr. Noura M. Al-Otaibi⁦2026-10-29⁩

Coming up

By date

  1. 292026-10Change Control BoardMeeting · Weekly
  2. 292026-10Leadership and watchersDashboard · Daily
  3. 302026-10Process-owning departmentsWorkshop · Fortnightly
  4. 012026-11Project sponsorReport · Weekly
  5. 022026-11National Information Center (Nafath)Meeting · Weekly
  6. 022026-11Main vendorMeeting · Weekly
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close