Mueen Digital Platform — Release 4
Remove from watchlistOne platform for 68 e-judicial services — filing a case, following it, attending hearings, receiving judgments — with Nafath sign-in and links to government agencies through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Planned 67%
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control15 February 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth