Mueen Digital Platform — Release 4
Remove from watchlistOne platform for 68 e-judicial services — filing a case, following it, attending hearings, receiving judgments — with Nafath sign-in and links to government agencies through the Government Service Bus.
Budget (BAC)
Actual cost
60% of budget
Progress
Planned 67%
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control15 February 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+42 days vs approved
- Critical activities
- 14
- of 34 open activities
- Late activities
- 27
- past their baseline finish
- Schedule performance
- 0.87
- earned ÷ planned value
- Next milestone
- in 15 days
- Wave 1 development complete (24 services)
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
33 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 34 open activities, data date 2026-10-28
The critical path runs through 9 activities with no float
“Defendant-agency notice & reply APIs” needs a pace 6.5× faster than it has kept
It earned 33% in 90 days; the forecast assumes the rest in 28 days. At the pace so far it finishes on 2027-04-29.
“Pending-case migration & reconciliation” has no successor
Its 91 days of float is not real — it feeds nothing. Suggested link: → “User acceptance testing”.
Effect on the finish: +13 days
Milestones slip 24 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
“Wave 2 detailed design (appeals & reconsideration petitions)” has no successor
Its 183 days of float is not real — it feeds nothing. Suggested link: → “Cut-over & launch readiness”.
No effect on the finish, but it closes the logic
“Wave 1 stabilisation & defect fixing” has no successor
Its 132 days of float is not real — it feeds nothing. Suggested link: → “User acceptance testing”.
No effect on the finish, but it closes the logic
“Internal judicial systems integration” has no successor
Its 101 days of float is not real — it feeds nothing. Suggested link: → “Cut-over & launch readiness”.
No effect on the finish, but it closes the logic
The critical chain
In date order, to final acceptance
Near-critical