10My actionsNotifications

RSK-0001Unified Digital Services Platform

Nafath and SADAD integration interfaces not ready on time

16HighOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The platform depends on a shared NIC test environment, and the updated SADAD specifications have not been delivered

Preventive controls

  • Reserve a dedicated NIC test environment for three months
  • Build a SADAD interface simulator so development continues without the environment
  • Weekly checkpoint with the Nafath team on interface readiness

3 / 4

Event

Nafath and SADAD integration interfaces not ready on time

16HighTrigger

The test environment is still unavailable on 2026-11-15, or integration testing fails twice in a row

Contingency

Launch wave 1 with the services that need no e-payment, and move fee-based services to wave 2

Impact

A 40-day integration slip pushes wave 1 and the official launch past March 2027, with about SAR 2.4M of extra vendor team cost

SAR 2.4M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 2.4M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 2 days ago

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

    Automatically at 15 days unreviewed · in 13 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 18 days
  4. 4

    Executive committee

    Eng. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦4⁩ done
  • Reserve a dedicated NIC test environment for three months

    Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa
    In progressIn 7 days2026-11-0424 Jumada I 1448 AH
  • Build a SADAD interface simulator so development continues without the environment

    Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@alwaha.gov.sa
    In progressIn 13 days2026-11-1030 Jumada I 1448 AH
  • Weekly checkpoint with the Nafath team on interface readiness

    Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa
    Done⁦2026-10-21⁩2026-10-2110 Jumada I 1448 AH
  • Approve a phased integration test plan instead of one big-bang test

    Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@alwaha.gov.sa
    Overdue3 days overdue2026-10-2514 Jumada I 1448 AH

Trigger

The test environment is still unavailable on 2026-11-15, or integration testing fails twice in a row

Contingency

Launch wave 1 with the services that need no e-payment, and move fee-based services to wave 2

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close