PRJ-2026-031On track11Benefits RealizationScrum

Court Appointment Booking Service

Add to watchlist

One booking service for beneficiary desks in the courts, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work8M⁦16⁩ elements
Unallocated contingency246KSAR 410K
Budget at completion8.2MPRJ-2026-031
Weighted progress⁦100%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project469⁦2024-04-07⁩⁦2025-07-20⁩⁦100%⁩7.957.96—
1
Phase105⁦2024-04-07⁩⁦2024-07-21⁩⁦100%⁩0.640.64—
1.1
WBS element65⁦2024-04-07⁩⁦2024-06-11⁩⁦100%⁩0.320.320 / 1
1.2
WBS element65⁦2024-05-17⁩⁦2024-07-21⁩⁦100%⁩0.320.321 / 2
2
Phase105⁦2024-06-27⁩⁦2024-10-10⁩⁦100%⁩1.351.35—
2.1
WBS element65⁦2024-06-27⁩⁦2024-08-31⁩⁦100%⁩0.680.681 / 1
2.2
WBS element65⁦2024-08-06⁩⁦2024-10-10⁩⁦100%⁩0.680.681 / 2
3
Phase145⁦2024-09-16⁩⁦2025-02-08⁩⁦100%⁩3.183.18—
3.1
WBS element64⁦2024-09-16⁩⁦2024-11-19⁩⁦100%⁩1.061.061 / 1
3.2
WBS element65⁦2024-10-26⁩⁦2024-12-30⁩⁦100%⁩1.061.061 / 1
3.3
WBS element64⁦2024-12-06⁩⁦2025-02-08⁩⁦100%⁩1.061.061 / 2
4
Phase105⁦2025-01-15⁩⁦2025-04-30⁩⁦100%⁩1.591.59—
4.1
WBS element65⁦2025-01-15⁩⁦2025-03-21⁩⁦100%⁩0.800.801 / 1
4.2
WBS element65⁦2025-02-24⁩⁦2025-04-30⁩⁦100%⁩0.800.801 / 2
5
Phase105⁦2025-04-06⁩⁦2025-07-20⁩⁦100%⁩1.191.19—
5.1
WBS element65⁦2025-04-06⁩⁦2025-06-10⁩⁦100%⁩0.600.601 / 1
5.2
WBS element65⁦2025-05-16⁩⁦2025-07-20⁩⁦100%⁩0.600.601 / 1
Total⁦100%⁩7.957.96