WRDA/2025/017
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
75% of the current value paid
Paid
10.7Mof a current value of SAR 14.2M
Data governance advisory and master data policies per the National Data Management Office.
Payments against approved deliverables, within 30 days of approval.
Payment period
30 days
Retention
5%
Released at final acceptance
Advance payment
10%
Recovered from certificates
Penalty cap
6%
Of the contract value
Defects liability
Not applicable
After substantial completion
Bar: paid share of the value; gold mark: today
Met: 3 of 3
| Measure | Target | Achieved | Breach penalty |
|---|---|---|---|
| Deliverable turnaround | within 10 working days | average 7 days | — |
| Key staff availability | 100% of approved key staff | 100% | — |
| Monthly report | by the 7th of the month | on time | — |
Integration-ready for EtimadIntegration-ready
Etimad reference: 2504300615
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
Bank guarantees and insurance policies with their expiry